ID Task Name Duration Start Finish Status Actual Finish
1 Preliminary Work 17 days 22-Jan-07 13-Feb-07 Done 7-Feb-07
2 ---Review Processes 3 days 22-Jan-07 24-Jan-07 Done Jan 07
3 ---Document Processes 2 days 25-Jan-07 26-Jan-07 Done Jan 07
4 ---Purchase Server 1 day 29-Jan-07 29-Jan-07 Done Jan 07
5 ---Configuration Inputs 2 days 30-Jan-07 31-Jan-07 80% Done Feb-5-07
6 ---Download Mifos 1 day 1-Feb-07 1-Feb-07 Done 28 Jan 07
7 ---Install Mifos at Jitegemea 1 day 2-Feb-07 2-Feb-07 Done 7-Feb-07
8 ---Review Products Setup with Client 1 day 5-Feb-07 5-Feb-07 Done
7-Feb-07
9 ---Customise Mifos 3 days 6-Feb-07 8-Feb-07 Done
12-3-07
10 ---Carry out General Training 2 days 9-Feb-07 12-Feb-07 Done
13-3-07
11 ---Setup Mifos Test directory 1 day 13-Feb-07 13-Feb-07 Done
12-3-07
12 Capture Data as at 31st Dec 2006 31 days 14-Feb-07 28-Mar-07

13 ---Setup Clients 3 days 14-Feb-07 16-Feb-07 Done
28-Mar-07
14 ---Capture Loans 10 days 19-Feb-07 2-Mar-07 Done
16-May-07
15 ---Capture Savings 5 days 5-Mar-07 9-Mar-07 Done 11-May-07
16 ---Generate Status Reports 5 days 12-Mar-07 16-Mar-07 Done 28-Mar-07
17 ---Review with Client 2 days 19-Mar-07 20-Mar-07 Done 21-May-07
18 ---Refine 5 days 21-Mar-07 27-Mar-07 Done 24-May-07
19 ---Sign-off Take-on 1 day 28-Mar-07 28-Mar-07 Done 25-May-07
20 Capture January 2007 Data 22 days 29-Mar-07 27-Apr-07

21 ---Train Client 2 days 29-Mar-07 30-Mar-07 Done

22 ---Supervise Data entry 15 days 2-Apr-07 20-Apr-07 Done
23 ---Generate Reports 5 days 23-Apr-07 27-Apr-07 Done
24 ---Sign-off January 1 day 29-Mar-07 29-Mar-07 Done 12-Jun-07
25 Design Interface with Pastel 10 days 30-Apr-07 11-May-07

26 ---Define Procedures 1 day 30-Apr-07 30-Apr-07 Done
21-May-07
27 ---Generate Summary Data from Mifos 2 days 1-May-07 2-May-07 Done 19-Oct-07
28 ---Post manually to Pastel 1 day 3-May-07 3-May-07

29 ---Code interface file 2 days 4-May-07 7-May-07 Done 19-oct-07
30 ---Test interface posting 3 days 8-May-07 10-May-07 Done 26-Nov-07
31 ---Train Users 1 day 11-May-07 11-May-07 Done 6-Dec-07
32 ---Sign-off Interface 1 day 30-Apr-07 30-Apr-07

33 Document Project Report 5 days 14-May-07 18-May-07 In progress

34 Supervise Feb Data 15 days 21-May-07 8-Jun-07 Done
35 Supervise Mar Data 10 days 11-Jun-07 22-Jun-07 Done

 

 

 

 