Home > Developers > QA & Testing > v1.1 Test Schedule and Status
Document Actions

v1.1 Test Schedule and Status

Test Schedule

The v1.1 project test schedule (xls document) is describes the overall dates and resource allocation for the v1.1 testing effort.  This schedule is still being developed and the dates are not entirely accurate at this time.

 

Test Status

During the v1.1 project, the test efforts will be tracked using a dashboard based on the model first created by James Bach.  In addition, metrics will be collected on test cases and reported issues during testing cycles.

  1. Dashboard Status
  2. Test Case Status
  3. Issue Tracking Metrics

Dashboard Status

The priority, level of effort, coverage, assessment, and assignments for the various 1.1 testing tasks are documented in the testing dashboard (xls document).  The following categories and possible values are used with the dashboard:

Effort
None Not testing; not planning to test.
Start No testing yet, but expect to start soon.
Low Regression or spot testing only; maintaining coverage.
High Focused testing effort; increasing coverage.
Pause Temporarily ceased testing, though area is testable.
Blocked Can’t effectively test, due to blocking problem.
Ship Going through final tests and signoff procedure.


Test Coverage
0 We have no good information about this area.
1 High Priority Test passing
1+ Most High Priority Tests Passing 
2 Medium Priority Tests - common & critical tests executed.
2+ Most High and Medium Priority Tests Passing
3 All Test Cases Executed
3+ All Test Cases Passing


Assessment
Green No known or suspected showstoppers
Yellow Possibly unknown showstoppers
Red Showstoppers or blocked areas
White Not ready for testing

Test Case Status

This status will be published later in the project.

Issue Tracking Metrics

Issue tracking metrics can be viewed here (xls document).

 

last modified 2008-03-05 09:56
Grameen logo