We are using an Agile Development Process to build the Mifos software as it allows us to maximize community input and involvement and to build new features in a smooth and efficient manner. 

Although you can access current builds at any time, we aim to release frequent releases of stable versions of the software that we recommend running in production. 

The following is the process we are going through to build and test v1.1, and the tentative dates for each milestone.  These dates are subject to change at any time, and we will be updating this page to reflect any changes that might arise throughout the process.

Patch Freeze

Feb 1 2008

Last day for the community to submit new feature patches for inclusion in v1.1.
Feature Freeze

Feb 15 2008

All high-level modules are code complete. Developers now focus on bug fixes.  Only patches for bug fixes will be accepted after this date.
Project Code Freeze

Mar 15 2008

After this date, only bugs deemed vital for the release by QA are fixed by developers. Otherwise no code check-ins are allowed.
v1.1 Release

Apr 30 2008

Please reach out to the developer mailing list if you have any further questions.